Holtec 近日宣布完成了帕利塞兹(Palisades)核电站的主要翻新工程,包括蒸汽发生器维修和压力容器检查。然而,尽管实现了这些技术里程碑,该项目仍多次延期。在错过了原定的 2025 年底重启目标后,Holtec 已放弃了明确的时间表,转而使用含糊的措辞,仅承诺“在核电站准备就绪时”恢复运营。 虽然该公司已获得美国能源部 15 亿美元的贷款,并在应对环保人士的法律挑战中取得关键胜利,但仍有超过 5000 项任务尚未完成。随着 Holtec 为潜在的首次公开募股(IPO)做准备,该项目未能兑现最初备受期待的时间表,引发了外界的质疑。 帕利塞兹核电站最初被誉为业内提升核能产能最可行的“快速获胜”项目。然而,持续的延误表明,重启退役反应堆的复杂程度和执行难度可能超出了支持者的预期。最终,这些延误削弱了该行业的核心论点,即重启核电站是扩大核能规模最快、风险最低的途径。

相关文章

原文

Holtec announced last week that the major refurbishment projects at Palisades are complete.

Reactor vessel inspections, head penetration replacements, steam generator tube refurbishment, primary system decontamination, and operator training all wrapped up. New fuel now sits on site, ready for loading. The company called it a "watershed moment" and shifted focus to grinding through the remaining work.

Yet there is still no restart date…

     “Holtec International remains on track to restart operations at Palisades in October 2025

These are the comments provided by a Utility Dive article in 2025 after they spoke with Holtec’s International Director of Government Affairs and Communications Patrick O’Brien.

Needless to say, that date has passed. Starting earlier this year, the company pivoted to the vaguer line that Palisades would restart "when the plant is ready for long-term operations." CEO Kris Singh told the Financial Times he still expects the plant back this year, ahead of the March 2027 power supply contract. But "this year" is now half over with no firm schedule attached.

When the $1.5 billion DOE loan closed in 2024, expectations centered on a late 2025 restart. As the first deadline came to pass near the end of 2025 and the beginning of 2026, material issues, particularly with steam generators, had pushed the target into the middle of 2026. 

Each update added a few more months. Now the language has softened further into "steady progress" and "when ready." More than 5,000 individual work activities remain on the checklist. Most are described as routine maintenance, testing, inspection, and operational readiness items. 

The legal and financial pieces have at least moved forward. A federal court dismissed the environmental groups' lawsuit challenging the NRC exemption that allows a decommissioned plant to restart. 

Holtec is also preparing an IPO that multiple outlets peg at a roughly $10 billion valuation.

Palisades was always presented as the easiest restart project on the table. An existing plant on an existing site, with a recently operating license framework, the first major DOE loan guarantee, and novel NRC regulatory pathways created specifically to enable it. If any restart should have translated funding, approvals, and major refurbishment work into electrons on the grid without prolonged slippage, this was the one. 

The repeated movement of internal targets and the current shift to “when the plant is ready for long-term operations” instead makes reactor restarts look more uncertain and execution-heavy than simply licensing and building a new plant from scratch. That undercuts the core industry argument that restarts represent the lowest-risk, fastest path to new nuclear capacity.