Norway greenlights first full-scale ship tunnel

原始链接: https://eandt.theiet.org/2026/06/18/norway-greenlights-world-s-first-full-scale-ship-tunnel

挪威一项旨在绕过恶劣海况的重大隧道工程正迈向 2027 年的开工日期。该项目涉及复杂的“钻爆法”作业,需要开挖约 300 万立方米的岩石,并建造一道临时挡水墙。由于当地道路条件较差,所有建筑材料都将通过海运送达。 挪威沿海管理局目前正在评估三家主要承包商的最终投标书:AF Gruppen、Eiffage Génie Civil 以及由 Skanska 和 Vassbakk & Stol 组成的联合体。在挪威议会于 6 月 19 日敲定预算,并经过合同授予后的静默期后,该项目已正式步入正轨。 该项目早在几十年前就已提出,克服了多年的经济争论,并于 2013 年正式被纳入国家交通规划。继 2021 年获得政府最终批准后,该隧道现定于 2031 年向船只开放。

抱歉。
相关文章

原文

Tunnelling through a thick rock layer requires a ‘drill and blast’ process, with materials delivered by sea, owing to limited local road infrastructure. A rock wall will be used to keep the tunnel free of water during construction, during which approximately three million cubic metres of rock will require removal.

The Norwegian parliament is preparing to finalise the budget for the project on 19 June, with an eye to starting construction works in early 2027.

The tender competition for the main contract has been ongoing for nearly two years. In April, the Norwegian Coastal Administration received final bids from AF Gruppen, Eiffage Génie Civil and the Skanska/Vassbakk & Stol consortium.

Once the contract award is announced, there will be a standstill period for any complaints before it can be signed as planned. 

After conflicting reports about the economic feasibility of building the tunnel during the 2000s, it was finally included in Norway’s National Transport Plan in 2013. Debates continued about whether to press ahead with the project until 2021 when the Norwegian Ministry of Transport and Communications finally gave approval for preparations to begin. It is expected to be open to boat traffic from 2031.